Civil Model Jury Charge 4.30B BUILDING CONTRACTS — EXTRAS
A.
Where the Contract is Silent as to the
Changes or Extras
Where
“extras” are claimed by the builder the first issue to be resolved is whether
the items claimed as extras were included within the terms of the basic
contract between the owner and the builder.
If they were, the builder is not entitled to additional
compensation. If they were not included
within the basic contract the builder is entitled to additional compensation
only if the extras were requested or authorized by the owner.
If
the extras were requested or authorized by the owner, and if there was an
agreement between the parties as to the price to be paid for such extras, the
builder is entitled to receive the agreed price.
If the extras were requested or
authorized by the owner, and there was no agreement as to price, the builder is
entitled to be paid the reasonable value of the extras.
Cases
and Commentary:
Whether a
builder is entitled to compensation for extras is determined by basic contract
principles. The issue is whether there
was an agreement express or implied that the builder be paid. If what the builder did was comprehended
within the construction contract, there are no extras. See
Terminal Construction Corp. v. Bergen
County, etc., District Authority, 18 N.J. 294 (1955). Moses
v. Edward H. Ellis, Inc., 4 N.J.
315 (1950) is an illustration of the rule.
The controversy there was between contractor and sub-contractor. The issue was whether the sub-contractor was
entitled to payment for pouring concrete into uneven rock in order to bring it
to “pay” lines [lines set out in drawings].
He/She was held entitled to payment, but as specified in the contract, although
this was in a sense “extra work”. If the
work was performed without the owner’s request or authorization, and the owner
has not agreed to pay, he/she is not liable.
17A C.J.S., Contracts, Sec. 371 (1), p. 401. If the owner has requested or authorized the
work, he/she is liable. 3 Corbin on Contracts, Sec. 564, p. 296
(1965).
If there has been an agreement as to price, that agreement would
control. Sbaraglio v. Vicarisi, 110 N.J.L.
280 (E. & A. 1933). In the absence
of agreement quantum meruit would be the only means for
determining the amount of compensation. Kolmetsky v. Pellicoff, 6 N.J. Misc.
315, 141 Atl. 10 (Sup. Ct. 1928), aff’d, 105 N.J.L. 240 (E. & A. 1928); see
also Shapiro v. Solomon, 42 N.J. Super.
377 (App. Div. 1956).
B. Where the Contract Prohibits Changes
without Written Authority
Since this contract contains a
provision that the owner shall not be liable for extra work unless he/she has
authorized it in writing, the builder cannot recover for services rendered or
materials supplied in addition to those specified in the contract unless the
builder proves that there has been a new and subsequent contract that he/she be
paid for such additional work or materials (extras). This subsequent contract may be an oral
agreement or may be implied from the conduct of the parties. It must show an agreement by the parties that
the extra work was to be done and an agreement by the owner to pay for it.
Cases
and Commentary:
Both
cases and texts have spoken in terms of waiver of the provision requiring
extras to be authorized in writing. 13 Am. Jur.2d, Building Contracts, Sec. 22
p. 24. However, the issue involved is
whether there was a subsequent contract for adequate consideration covering the
work. 3A Corbin on Contracts, Sec. 756, p. 505 (1963). The governing rule is that, “parties to an
existing contract may, by mutual consent, modify it.” Bohlinger
v. Ward & Co., 34 N.J. Super. 583, 587 (App. Div. 1955), aff’d 20 N.J. 331 (1956). The parties
cannot be prevented from entering into a new contract, written or oral, by a
provision that a subsequent agreement not in writing shall not be binding. Headley
v. Cavileer, 82 N.J.L. 635 (E.
& A. 1912); Guizzette v. Katrek,
124 N.J.L. 461 (Sup. Ct. 1940); Lord Construction Co. v. United States,
28 F.2d 340 (CA 3, 1928); In Re
Fleetwood Motel Corp, 335 F.2d
863 (CA 3, 1964); Sheyer v. Pinkerton Construction
Co., 59 Atl. 462 (N.J. E. &
A. 1904); Denoth v. Carter, 85 N.J.L.95 (Sup. Ct. 1913); Rizzolo v. Poysher, 89 N.J.L. 618 (E. & A. 1916), Fortunato v. Cicalese, 93 N.J.L. 461 (E. & A. 1919).
In Homeowners Construction
Company v. Borough of Glen Rock, 34 N.J.
305, 316-17 (1961), the Court required clear and convincing proof when a party
alleges oral modification of a written agreement that expressly prohibits such
oral modification.